Data Center
Ashburn, VA
GC: HITT Contracting
Architect: Corgan Architects
Square Feet: 280K
Contract Value: $9M
Daily Manpower Range: 50-100
Schedule: 28 weeks
Type: Technology
Scope: Drywall
–––––––
Rock Spring’s scope included the core & shell and 5 data halls with each space going on simultaneously. We had an extensive crew of over 100 employees at times working double shifts, 24/7 to meet the demand from the customer. In all, we completed our scope of over 280K square feet and 30 MW of space in about 6 months.