GC: ​​Davis Construction 

Architect: Studios Architecture 

Square Feet: ​500K 

Daily Manpower Range: 40-50

LEED: Yes

Scope: Demolition

–––––––

Rock Spring kicked off this full building repositioning which including the removal of 12 floors of office space, a façade opening, and approximately 5,000 SF of elevated slab removal.  Rock Spring also furnished and installed all interior and exterior temporary barrier systems for the project.
 